FELTON, Santa Cruz County — November 8, 2026. Pedestrian improvements along Highway 9 continue next week, with Caltrans planning sidewalk, curb and retaining-wall work during the week of November 9–13 near the approach to Graham Hill Road and Felton Empire Road.
What is being built?
The Highway 9 Felton Pedestrian Safety Improvements Project includes a sidewalk and bikeable shoulder on the southbound side of the highway between the school complex and downtown. Caltrans says a temporary concrete barrier closing a southbound lane near the intersection protects crews and is expected to stay in place through February 2027.
Upcoming construction details
From November 9 through November 13, crews plan retaining-wall work around post miles 6.4–6.6 and sidewalk, curb and gutter work around 6.6–6.9. The state lists additional work November 12–13, including wall removal around mile 6.9. A concrete pour is scheduled Friday, November 13, 3:30–6 a.m., with one-way reversing traffic control in the work zone.
Critical timing: concrete pour before dawn on Friday
November 12 update: Caltrans reaffirmed a planned concrete pour on Friday, November 13, from 3:30 to 6 a.m., bringing reversing one-way traffic control on Highway 9 near Graham Hill Road, approximately post miles 6.4–7.6. During daylight hours November 12–13, crews are also scheduled to work on a wall near post mile 6.9 and build a sidewall at 7.1–7.2. The long-term southbound lane barrier is expected to stay through February 2027 while the safety project continues.
These are published work plans; Caltrans has not verified a specific minute-by-minute delay for every motorist. Allow extra time, follow flaggers and temporary signals, and check QuickMap for changes. November 6 District 5 advisory.
What should local residents do?
Allow extra time near the school and downtown, follow temporary signals, and do not assume the sidewalk is open during construction. The proposed public benefit is safer walking and cycling; the project schedule is not proof the improvements have been completed. For changing conditions check QuickMap and the November 6 Caltrans advisory.
Source: Caltrans District 5, November 6, 2026 project update.
Support Felton News
Choose how to support Felton News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Felton News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Felton News
- Santa Cruz County Funds Free Wildfire Zone-0 Clearing for 100 High-Risk Homes: What Felton Residents Should Verify →
- Felton Fire District: Craig Winter and Norman Crandell Lead for Two Board Seats →
- Felton’s Quail Hollow Ranch Adds Six Miles of Trails Across 80 Acres: County Schedules October 26 Opening →
- Felton Highway 9 Sidewalk Project: Lane Barrier Near Graham Hill May Remain Until February →
- Felton News: October 22 Highway 9 Sidewalk Town Hall Offers Residents a Say on Pedestrian Safety →
COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.